- ºÚÁϳԹÏÍø
- Repairs
Build on the Rock
Page Navigation
- Overview
- Athletic Upgrades
- Language Immersion School
- Media Center Upgrades
- New District Office
- New Makerspaces
- Northside Elementary
- Renovations & Additions - ATC
- Renovations & Additions - Ebenezer
- Renovations & Additions - Ebinport
- Renovations & Additions - Rosewood
- Renovations & Additions - Sunset Park
- Renovations - Rawlinson Road
- Repairs
- Restroom Upgrades
- Safety & Security
- Transportation
- Sullivan Middle School
- Renovations & Additions - York Road
Building Systems Repairs & Replacements
-
Project Description:
There are a number of projects in the district that are either repairs or scheduled maintenance of aging or failing systems.Project Photos:
Rawlinson Road Middle School
The "drop ceiling" system and ceiling tiles at Rawlinson Road Middle School were replaced in August 2016.Additional ceiling tile replacement - Summer 2017
Renovated Family & Consumer Sciences Classroom - Summer 2017
Rock Hill High School
Exterior cladding repair. Over time, water has leaked behind the brick facing on Buildings D and E causing the brick anchors to rust. This project is a pre-emptive replacement to minimize safety risk, and includes replacement of building windows as an energy retrofit. Expected completion: August 2017
January 13, 2017 - D Building
February 8, 2017 - D Building, left, and E Building
April 21, 2017
They're laying brick on D and E buildings.
Exterior Work Complete, including new windows in D and E buildings
Northwestern High School
Exterior cladding repair. Over time, water has leaked behind the brick facing on Buildings D and E causing the brick anchors to rust. This project is a pre-emptive replacement to minimize safety risk, and includes replacement of building windows as an energy retrofit. Expected completion: August 2017
Northwestern - February 2017
Northwestern D Building - March 22, 2017
Northwestern D Building with new "skin" and windows - June 12, 2017
Roof Replacements
Independence Elementary
The roof surface at Independence Elemtnary is being replaced, and as part of a separate project, there will be a solar panel roof system installed over the entire roof later this year.
April 21, 2017Ebinport Elementary
Completed August 2016
Driveway & Parking Improvements
Central Child Development Center
The front driveway,which is utilized for bus pickup and dropoff as well as visitor parking, is being improved. Additionally, a gravel parking lot for staff is being enlarged and paved to improve the campus and accessibility.
July 6, 2017
July 18, 2017 - new parking lot at Central Child Development Center
New Parking and Front Drive Complete